[ad_1] The following activities are part of a project to be scheduled using CPM: Activity Immediate Predecessor Time (Weeks) A – 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G
[ad_1] The following activities are part of a project to be scheduled using CPM: Activity Immediate Predecessor Time (Weeks) A – 6 B A 3 C A 7 D C 2 E B, D 4 F D 3 G